Construction project cost overrun and time delay An evaluation of extent and influential factors Mahlet A. Hailemariam; Supervisor: Tahir Çelik
Dil: İngilizce Yayın ayrıntıları:Nicosia Cyprus International University 2015Tanım: VIII, 100 p. color chart, table, color figure 30.5 cm CDİçerik türü:- text
- unmediated
- volume
Materyal türü | Geçerli Kütüphane | Koleksiyon | Yer Numarası | Durum | Notlar | İade tarihi | Barkod | Materyal Ayırtmaları | |
---|---|---|---|---|---|---|---|---|---|
Thesis | CIU LIBRARY Tez Koleksiyonu | Tez Koleksiyonu | YL 554 H25 2015 (Rafa gözat(Aşağıda açılır)) | Kullanılabilir | Civil Engineering Department | T613 |
CIU LIBRARY raflarına göz atılıyor, Raftaki konumu: Tez Koleksiyonu, Koleksiyon: Tez Koleksiyonu Raf tarayıcısını kapatın(Raf tarayıcısını kapatır)
Includes CD
Includes bibliography (78-82 p.)
'Abstract The construction industry is a huge industry that affects the economy of a country in a significant way. Cost overrun in construction is said to happen when the final cost of the project exceeds the estimate of the budget. Time delay or time overrun are terms that are used to describe the delay of construction work from the contractual or the planned duration. The objective of this research is to evaluate the extent of time and cost overrun in the Ethiopian construction industry. Moreover, to identify the factors that are causing time delay and cost overrun in Ethiopia. The research is divided in to two. The first part is a detail case study done on 9 governmental projects each worth more than 1 million USD and all commenced and completed in the last 15 years. Cost overrun observed ranges from 8% to 75.90% with an average of 30.6% and standard deviation of 23.1. The time delay observed in the case study ranges from 56.81% to 230.80% of the contractual time duration of the project with an average of 111.63% and a standard deviation of 58.1. The analysis of responses from 104 professional in client, consultant and contractor offices using relative importance weights (RIW%), have shown that the most influential factors for cost and time overrun are the factors related to staff. Lack of qualified staff, inflation, escalation of material prices, poor coordination between the construction project manager and high level management are the highly ranked factors. One of the challenges of this research was accessing data of projects to be used for the case study. Further works can be done by classifying the projects into governmental, private and public projects. KEY WORDS: Cost overrun, time delay, KJ method, Relative Importance Weight, Radar charts, Ethiopian construction industry'
1 Introduction
1 Scope and objective
4 Methodology
5 Challenges
6 Acheivements
7 Guide to Thesis
8 Literature review
8 Introduction
9 What is cost overrun in Construction
9 Extent of construction cost overrun in the world
12 Time delay
15 Methodology
16 PART ONE
16 Case Studies
16 Modjo Awash Project
18 Woldia - Almata
20 Awash -Harar
22 Betermariam -Wukro Project
24 Debramariam Merawi Project
25 Hirna Kulibi Project
27 Ambo University Dormitory Buildings
28 Ambo University Admistration building and Site work
29 Addis Ababa University Classroom Blocks
31 Summary of Data
34 PART TWO
34 Questionnaire
41 Representative Sample Selection
43 Relative Importance Index (RIW %) and Ranking
50 Result and Discussion
51 Results
51 Radar Charts
68 Discussion
68 Case Study
70 Questionnaire Survey
74 Mitigations
75 Conclusions and Future works
77 Conclusion
77 Furure works
78 Bibliography
83 Appendix